Section F1.00 - General Information

F1.01 - Introduction

  • The Federal Highway Administration's defines eConstruction as a paperless construction administration delivery process that includes electronic submission of all construction documentation by all stakeholders, electronic document routing/approvals (e-signature), and digital management of all construction documentation in a secure environment allowing distribution to all project stakeholders through mobile devices.
  • The Delaware Department of Transportation is accomplishing this by first focusing on the electronic recording of Inspector Daily Reports and electronic submittal of documents using the Primavera Unifier software. Unifier will eventually be used to facilitate the electronic administration of all aspects of construction documentation from cradle to grave as well as the electronic submittal of contractor payments. In addition, we are moving towards adding 3D Modeling to our design process with more information on that process being added to this webpage as those processes are defined.
  • The information below explains the different software applications that the Department is using to facilitate the eConstruction effort. Any questions on this can be directed to the Senior Project Controls Coordinator, Billy Sweeney at su.ed.etats|yeneews.yllib#su.ed.etats|yeneews.yllib.


Section F2.00 - Software

F2.01 - Oracle Primavera P6 EPPM

  • What is it?
    • Primavera P6 EPPM is a web-based enterprise project portfolio management software owned by Oracle, Inc. Click this link for more information from Oracle.
  • How is it used?
    • The Delaware Department of Transportation is using P6 EPPM as our project scheduling tool and to assist in the development and performance tracking of our 6-year Capital Transportation Plan. It is also used for the review of contractor CPM schedules during the construction phase.
    • Future use includes providing access to Contractor's that are required to submit a CPM schedule as part of the Contract requirements. This CPM Specification will eventually be changed to require contractor's or their consultants to create and maintain their CPM schedule in DelDOT's P6 environment.
    • Currently using version 15.2.
  • How do you access it?
    • P6 is accessed by going to https://P6.DelDOT.gov
    • Access to P6 is currently only granted to DelDOT employees or consultants of DelDOT with an expected role of updating the schedule of a project or program at DelDOT.
    • For more information, send an email to Billy Sweeney, Senior Project Controls Coordinator, at su.ed.etats|yeneews.yllib#su.ed.etats|yeneews.yllib.


F2.02 - Oracle Primavera Unifier

  • What is it?
    • Primavera Unifier is a web-based project lifecycle management application owned by Oracle, Inc. Click on this link for more information from Oracle.
  • How is it used?
    • As the framework for our eConstruction effort.
    • All capital construction projects administered by the Department of Transportation Solutions with an NTP after April 10th 2017 will use Unifier for entering, tracking and approving Inspector Daily Reports.
    • Future phases of the Unifier Implementation to be completed by the end of Calendar Year 2017 include the tracking and approval of all Construction Document Management (RFI's, submittals, subcontractor approvals, etc…) and Construction Cost Management (estimate creation, approval, and transferring of payment requests to the FACTS application).
    • Further plans to incorporate the advertising and awarding of contracts, capital budget planning, project/program audit and closeout, and additional DBE tracking efforts are all being considered as well.
    • Currently using version 16.2.6.
  • How do you access it?
    • Unifier is accessed by going to https://Unifier.DelDOT.gov using any browser on any device with an internet connection.
    • From Apple IOS devices (iPhone or iPad), Oracle has developed a Primavera Unifier app. More information on this app can be access by click on this link.
    • Access to Unifier is currently only granted to DelDOT employees, consultants of DelDOT with a role in our eConstruction effort, or other partners deemed necessary to the administration of DelDOT projects.
    • For more information, send an email to Billy Sweeney, Senior Project Controls Coordinator, at su.ed.etats|yeneews.yllib#su.ed.etats|yeneews.yllib.


F2.03 - Bentley ProjectWise

  • What is it?
  • How is it used?
  • How do you access it?


Section F3.00 - General Documentation

F3.01 Oracle Primavera Unifier

  • User Documentation
  • User Training
  • Unifier Business Process (BP) Training info
    • Change Order Process
    • Progress Estimate Process
      • OVERVIEW: In Unifier, the Progress Estimate process is a two BP process. Pencil Estimate and Progress Estimate. First, a Pencil Estimate record must be initiated, reviewed, and acknowledged by the following roles: Project Resident, Contractor Project Manager, and Area Engineer. After the Pencil Estimate record is complete. The Area Engineer will continue the process by starting a Progress Estimate record. The Progress Estimate record must then be reviewed and acknowledged by the following roles: Area Engineer, Estimator, Contractor Project Manager, Group Engineer, and Assistant Director (Only if it is a Final Estimate). It is important that the Estimate Worksheet is accurate. The items and quantities on this report are an exact representation of what will be used in the Progress Estimate BP.
      • Pencil Estimate Process
        • OVERVIEW: The Pencil Estimate process is used to create the draft version of the Estimate that the Project Resident creates and sends to the Contractor Representative for initial acknowledgement. Then, after the Contractor Representative reviews, it is sent to the Area Engineer. All of these steps are fully contained within Unifier with automatic emails being sent to the person identified at each step. In addition, each step has the ability to send the record back to the Project Resident for a revision. See below for more information on the revision process.
        • Creating a Pencil Estimate Record
        • Project Resident Pre-Review
        • Contractor Review
        • Area Engineer Review
        • Additional Information: If it is determined that the Pencil Estimate needs to be corrected, the record should be sent to the revision step. This will send the record back to the responsibility of the Project Resident. At that point, based on the type of change that is required, a Price Approval, Change Order, and/or Quantity adjustment can be completed and approved by the appropriate people. Keep in mind that if a new item is needed, all 3 processes must be completed (Price Approval to add the item to the list of items, Quantity Adjustment to record the quantity to be paid for that period, and Change Order to officially add the item to the Contract so that it can be paid on a Progress Estimate. Once that is done, there are 2 options:
          • 1. If you are sure that the appropriate adjustments were made, simply move the record to the Contractor Review step
          • 2. However, its recommended that the Estimate Worksheet be verified first. Follow this video to manually run the Estimate Worksheet from the record: (Run Estimate Worksheet)
      • Progress Estimate process
        • OVERVIEW: The Progress Estimate process is used to create the final version of the Progress Estimate. This process is started by the Area Engineer then sent to the Estimator for further processing. At the Estimator step, the Estimator decides whether they want to automatically pull item quantities from the Approved Inspector Daily Reports (IDR) or manually enter each item. In the case where the Estimator decides to pull from the Approved IDRs, the Estimator does get a chance to review the estimate prior to sending the record to the Contractor Rep. The Contractor Rep will acknowledge the estimate and the record will be sent to the Group Engineer for review and acknowledgement. Finally, once the Group Engineer reviews and acknowledges, if the Estimate is identified as a Final Estimate, it will go to the Assistant Director for final acknowledgement. If the estimate is identified as an Interim Estimate, after the Group Engineer step, the record is sent to the Approved status and cannot be modified. At each step an email is automatically sent from Unifier to the responsible person with a PDF version of the Estimate Header sheet and Worksheet(s). The format of this PDF and information contained should be similar to what has been provided from other applications in the past.
        • Creating a Progress Estimate record
        • Estimator Review - Import from IDRs and Final Review
        • Estimator Review - Initial Review and Manual Input
        • Estimator - Advanced Material Payment
        • Estimator - Liquidated Damages and Retainage
        • Contractor Review
        • Group Engineer Review
        • Assistant Director Review (Final Estimate Only)
        • Additional Information: If it is determined that the Progress Estimate needs to be corrected, the record should be sent to the revision step. This will send the record back to the responsibility of the Area Engineer. At that point, based on the type of change that is required, a Price Approval, Change Order, and/or Quantity adjustment can be completed. Keep in mind that if a new item is needed, all 3 processes must be completed (Price Approval to add the item to the list of items, Quantity Adjustment to record the quantity to be paid for that period, and Change Order to officially add the item to the Contract so that it can be paid on a Progress Estimate. Once that is done, there are 2 options:
          • 1. If you are sure that the appropriate adjustments were made, simply move the record to the the Contractor Review step
          • 2. However, its recommended that the Estimate Worksheet be verified first. Follow this video to manually run the Estimate Worksheet from the record: (Run Estimate Worksheet)


F3.02 Bentley ProjectWise

  • User Documentation
  • User Training